Strategic coordination and constant collaboration
The scope of this project was vast, doubling the tennis center’s footprint to 40 acres, and the timeline for completion was rigidly tight. In order to meet the unmovable deadline—the 2025 Cincinnati Open—we moved from contract execution to final installation within six months. Achieving this feat required constant communication and collaboration not only among our team but with the various contracted partners working alongside us. Perhaps the clearest example of the level of coordination required was in the commercial kitchen, where we installed a custom wood tambour and stone expo wall fitted not only around MPE infrastructure but also commercial-grade cooking appliances and equipment. Given the tight timeline, there was no room for error, so we broke the installation into phases and held all-hands-on-deck meetings ahead of each phase to ensure efficient and flawless execution.